Card payment at EV chargers: what AFIR requires and by when

As of 27 October 2026 · Frank Höffken, Senior Payments Consultant

The EU Alternative Fuels Infrastructure Regulation, AFIR for short, requires ad hoc payment without a contract at public charging points. For many existing fast-charging points, the transition period ends on 1 January 2027. This page explains which charging points are affected, what is technically sufficient and what also applies in Germany.

The short answer

Since 13 April 2024, new public charging points have had to offer ad hoc payment, that is, payment without a contract or app. At 50 kW and above, this is only possible with a card reader or a contactless device. Below 50 kW, a QR code or online payment is also sufficient. Existing charging points of 50 kW and above on the TEN-T road network and in safe and secure parking areas must be retrofitted by 1 January 2027. There is no retrofit obligation for existing charging points below 50 kW.

Which charging points are affected

Charging pointObligationSince or from
newly built, 50 kW and abovecard reader or contactless device that can at least read payment cards13 April 2024
newly built, below 50 kWcard reader, contactless device or an internet-based method such as a QR code13 April 2024
existing, 50 kW and above, on the TEN-T road network or in a safe and secure parking arearetrofit a card reader or contactless device1 January 2027
existing, below 50 kWno obligation to retrofit a payment terminal
charging is free of chargeno obligation to offer ad hoc payment

This always refers to a publicly accessible charging point. One payment terminal may serve several charging points at one site. Payment must be possible with a payment instrument that is widely used in the EU.

What applies to prices and contract customers

AFIR also regulates how prices are displayed.

  • At 50 kW and above, the ad hoc price is based on the price per kilowatt hour. A fee per minute may also be charged to prevent long occupancy of the charger. Both must be displayed at the charging station before charging.
  • Below 50 kW, all price components must be clearly and easily available at the charging station, in this order: price per kilowatt hour, per minute, per charging session, other components.
  • Prices must be reasonable, easily comparable, transparent and non-discriminatory.
  • Anyone who offers automatic authentication, such as Plug and Charge, must give customers the choice to pay ad hoc or under a contract instead.

The first two rules apply to charging points built from 13 April 2024.

What also applies in Germany

A new Charging Station Ordinance (Ladesäulenverordnung) has applied since 1 January 2026. It replaces the 2016 version, no longer contains a payment rule of its own and serves to implement AFIR. The Federal Network Agency (Bundesnetzagentur) monitors the obligations under Article 5(1), (2), (7), (8) and (10) of AFIR, that is, payment, connectivity and technical requirements. It can require retrofitting and prohibit the operation of a charging point. Commissioning, decommissioning and changes of operator must be notified to the Federal Network Agency.

From 1 January 2027, breaches of the AFIR rules on price display can be fined up to EUR 100,000. The price authorities of the federal states are responsible. The basis is the Act amending German price indication law of 19 October 2026.

The European Commission is currently reviewing AFIR, including the rules on payment and price transparency. A proposal for amendments is expected by the end of 2026.

What operators need to decide now

  1. Take stock. Which charging points have 50 kW or more, and which are on the TEN-T road network or in a safe and secure parking area? Only these have to be retrofitted by 1 January 2027.
  2. One terminal per charging point or one per site. A central terminal saves devices, but it requires a clear assignment of each payment to its charging point.
  3. Card reader or contactless only. Both meet the obligation at 50 kW and above. The choice depends on the device, maintenance and your customers' cards.
  4. Acceptance contract and costs. For card payment, you need an acquirer. The fees are made up in the same way as in retail, plus the device, mobile connectivity and maintenance. This is explained on the page Card payment costs.
  5. Schedule. Devices, certification, installation and testing need lead time. If you are only starting in autumn 2026, you should set the order of your sites by obligation and revenue.

Frequently asked questions

Must every charger accept payment by debit card (girocard)?

At new public charging points of 50 kW and above, card payment by card reader or contactless must be possible. At existing charging points of 50 kW and above on the TEN-T network and in safe and secure parking areas, this applies from 1 January 2027. Below 50 kW, a QR code is also sufficient at new charging points. AFIR does not specifically require girocard, only a payment instrument widely used in the EU.

Do I have to retrofit my existing 22 kW charger?

No. For existing charging points below 50 kW, AFIR does not require a payment terminal to be retrofitted.

Is a QR code enough?

Only at new charging points below 50 kW. At 50 kW and above, a card reader or a contactless device is required.

May one terminal serve several charging points?

Yes, this is permitted at one site.

Who monitors this in Germany?

The Federal Network Agency (Bundesnetzagentur), on the basis of the Charging Station Ordinance of 23 December 2025. The price authorities of the federal states are responsible for price display.

Notice and sources

This page reflects the sources cited as of 27 October 2026 and is not legal advice.